Jetstone builds for the future
Text Tom Rampelbergh Beeld Jetstone

In autumn 2023, Jetstone almost doubled its production area in one fell swoop and is now gradually bringing the production lines into operation. At the same time, the worktop partner remains committed to Deurne, the Netherlands, where this is its third facility.

Deurne in the Netherlands remains the home base of worktop specialist Jetstone. “We recently opened a third production facility here,” adds Jetstone Marketing Coordinator Mark Joosten. “At a stroke, we have added 16,000 m², bringing our total production area to 34,000 m². By doubling our capacity, we are relieving the pressure on our two existing sites, both of which will remain fully operational, while also preparing for future growth. What began in an old pigsty in Deurne has grown into a sustainable worktop partner with 350 employees.”

Building during the pandemic
At first glance, Jetstone’s decision at the end of 2021 may seem bold. In the midst of the global COVID-19 pandemic, the worktop specialist decided to buy a plot of land and expand its facilities by no less than 16,000 m². “We want to use this to drive our international growth,” it said in an announcement that shared the plans and the first renders of the building. “The building will occupy a prominent site on the As in Deurne.” Pepers Architecten was immediately commissioned to create an attractive building, as the site would help shape Deurne’s skyline. Joosten says: “At Jetstone, we never rush into things. The decision to build a new production site was therefore carefully considered. So, despite the pandemic, we went ahead with our plans.”

Taking a step-by-step approach
When it unveiled its plans, Jetstone made clear that it was opting for a sustainable building, with no gas connection and solar panels on the roof to supply energy to the production lines and offices. “And that’s exactly what we’ve done,” Joosten tells us during the tour. “We’ve also developed a sustainable solution for water use. Just 2 percent of all the water we use is lost through evaporation. The remaining 98 percent is filtered and reused.” The first production line was brought into operation in autumn 2023, almost on schedule. Over the coming months, Jetstone will install the next production lines, gradually working towards full capacity. “Every production line is tailor-made,” Joosten explains. “We work with the machine manufacturers to design the production line exactly as we want it. Here too, we take a step-by-step approach to ensure the process is completed without a hitch. With offices and the Jetstone Academy also on site, this new facility will soon be buzzing with activity.”
Een zakelijke vraag aan Jetstone BVBA? Get in touch
Companies in this story
Keep following this
Get an email when a new story is published. No account needed.
- ThemeMaterials and finishes in balance
- SubjectGeneral
- CompanyJetstone BVBA