Permanent BORA site in Herford

BORA stands for innovative solutions for open-plan living spaces. The company is currently building an iconic structure in Herford, at the heart of Germany’s kitchen industry in East Westphalia. The new complex will offer visitors a varied brand and product experience, as well as an introduction to “the BORA principle”. For BORA, establishing a presence in the metropolitan region that is the centre of the kitchen industry is the next logical step. The new complex is intended to create added value for customers and trade partners, as well as for the city of Herford and its residents.
The new building on Ahmser Straße, the former site of a sports hotel, has permanently changed the face of Herford. Visible from a long way off, the unconventional building stands right beside the B 239 ring road and is easily accessible via the A2 for all visitors to Küchenmeile, Germany’s leading kitchen industry trade fair. “We want to be close to our trade partners and give as many interested customers as possible the opportunity to experience BORA live. That is why we are fully committed to investing in our Herford site,” says BORA founder and managing director Willi Bruckbauer. The project has also received unanimous local support and is seen as a positive signal for Herford as a business location.
The building has a total floor area of approx. 2,000 m². The new BORA site will serve as a permanent showroom for BORA and other partners in the interiors sector, and will be open to visitors on an ongoing basis. Space is currently being created across two levels for the BORA flagship store and showrooms. The 10,000 m² site will feature extensive landscaped areas and immersive experience spaces. An open-plan concept with huge windows has been chosen. The materials for the interior have been carefully selected. As a carpenter, Willi Bruckbauer has a keen eye for these details. The result promises to be the perfect setting for high-quality gastronomy. Showrooms rented to interested partners from a range of sectors will create an extensive product and brand experience, with culinary highlights for everyone interested in building, living and interior design.

A remarkable architectural feat for BORA
The building is anything but ordinary, both in the way it has been designed and constructed and in the speed and teamwork with which it is being realised. The concept for the impressive building in Herford was driven by the desire to create a form of construction never seen before. From the outset, it was clear that a project of this kind involved more risks than a conventional building, where the different floors are stacked one above the other as usual. But ‘innovation’ and ‘revolution’ are defining elements of BORA’s DNA, and the building is already visible from a long way off in Herford. Even from a great distance, it makes a striking impression on the city and perfectly reflects BORA’s vision, “The End of Normal”. Its innovative architecture and unique appearance show exactly what the company stands for.
Delivering pioneering architecture takes not only courage, but also the company’s tangible support. As with its sites in Raubling and Niederndorf (Austria), BORA is once again working with the architectural practice LORENZATELIERS, based in Vienna and Innsbruck. The team of planners and architects working on the project has been kept small. This allows decisions to be made quickly and makes the ambitious schedule achievable. The building is due to open in September 2023, just a year and a half after the laying of the foundation stone and in time for the start of Küchenmeile.

While discussions and coordination with the local authorities proceeded smoothly, global events did have some impact on the project. The biggest challenge for the contractors was the availability of materials, particularly the approximately 700 tonnes of steel required for the project.
The exterior and the projecting façade are clad in galvanised perforated panels with holes of varying sizes. From inside, this creates the impression of looking up at a starry sky. The metal cladding makes the impressive building look like an aircraft taking off, already hovering several metres above the ground. This effect is partly due to the delicate steel structure on which the building rests. The sheltered area beneath it will accommodate 80 parking spaces. As at BORA’s other sites, several electric vehicle charging points are also available.

Sustainability is a given at BORA
The iconic building is being constructed amid greenery. Large parts of the 10,000 m² site will be landscaped and developed as a natural environment this spring. Bruckbauer is keen to keep the ecological footprint of his new building low. Thanks to the German KfW 55 energy-efficiency standard, the building is highly energy-efficient. The energy it needs will be generated by photovoltaic modules on the roof. Water from a 200-cubic-metre sprinkler tank will serve as a storage reservoir for surplus energy. This provides an ingenious way of recovering heat for the building’s low-temperature heating system.
BORA Herford in brief:
Length: approx. 100 m
Height: approx. 13 m
Project floor area: 2,000 m2
Site area: 10,000 m2
Construction: steel frame with prestressed concrete elements
Façade cladding: galvanised perforated panels
Groundbreaking: 10 March 2022
Basement completed: early November 2022
Building structure completed: late December 2022
Topping-out: 15 February 2023
Opening: September 2023